Nicholas AndreouBarrister, Victorian Bar

Siemens v Vaughan Constructions [2006] VSC 452

Supreme Court of Victoria, 29 November 2006. Kaye J.

Hearing an injunction application as the trial of the action, Kaye J in the Practice Court of the Supreme Court of Victoria held that a notice referring a dispute to a contractual Dispute Committee of the parties' own representatives, whose role was to reach agreement, did not commence the kind of proceedings the Victorian Building and Construction Industry Security of Payment Act requires before a respondent may give security instead of paying an adjudicated amount, so Vaughan, the payment claimant, could enforce the guarantee [1], [2], [26], [28], [29].

What the court decided

By an agreement dated 30 June 2004 Vaughan Constructions subcontracted with Siemens to perform earthworks and main civil works for a gas turbine power station at Laverton North [2]. Vaughan referred a payment dispute to adjudication under the Building and Construction Industry Security of Payment Act 2002 (Victoria) [2]. The adjudicator determined that Siemens was liable to pay Vaughan $271,813.41 on a progress claim, with payment due on 31 October 2006 [2]. On 31 October 2006 Siemens sent Vaughan a Notice of Dispute under clause 25 of the contract and a bank guarantee for that amount [3]. The covering letter named Siemens' representatives for the Dispute Committee referred to in clause 25.2 [3]. The notice ended by stating that it was without prejudice to, and that the Contractor reserved, all its rights under the Contract and at law [4].

When Vaughan threatened to enforce the guarantee, Siemens sought an injunction to restrain its enforcement [5]. As the facts were not in dispute, the parties agreed that the matter should proceed as the trial of the action [1]. Siemens argued that its notice had commenced "other dispute resolution proceedings" under section 25(2) which had not been finally determined [8]. On that basis it said that section 25(5) made it unlawful for Vaughan to enforce the security until those proceedings were finally determined [6]. Vaughan's primary submission was that the phrase connotes curial or quasi-curial proceedings, and that the Dispute Committee was a conciliatory body lacking such processes [11]. Alternatively, it said the notice commenced nothing because it identified no tier of clause 25 and was without prejudice [11].

Kaye J first held that the notice, read with its covering letter, did refer the dispute to the Dispute Committee under clause 25 [13]. His Honour said the intended meaning of the "without prejudice" statement was "difficult to divine", but held that, whatever it meant, it did not negate that effect [14].

Kaye J accepted that the Act did not intend to supplant contractual provisions for resolving disputes [16]. However, the mere existence or articulation of a dispute is not enough, because section 25(2) requires that the respondent have commenced "proceedings" [18]. Construing the phrase eiusdem generis with arbitration proceedings, he held that it envisages the independent determination or adjudication of the dispute between the parties [19]. That reading was supported by section 25(5), section 25(6) and section 47(4), each premised on such proceedings ending in a "determination" [20]. He accepted that some informal building industry mechanisms may qualify, but held it essential that an independent person or persons decide the dispute, adhering to the "fundamental tenets of procedural fairness" [23].

That a reference to the Dispute Committee was a mandatory first step was relevant but not determinative, because a prerequisite to proceedings need not itself form part of them [24]. Nor was the final and binding effect of a mutual decision determinative, since a successful conciliation is equally final and binding [25]. In his Honour's view, clause 25.2 contemplated conciliation between the parties' representatives, rather than adjudication by an independent person [26]. The committee members were representatives of each party, in stark contrast to the "demonstrably impartial" adjudicator required under clause 25.3 [27]. The notice of dispute therefore did not commence any such proceedings under section 25(2) [28].

Because Siemens had not commenced such proceedings, Vaughan was entitled to enforce the security [29]. The claim for an injunction failed and his Honour held that the originating motion should be dismissed [30].

Why it matters

As Kaye J construed the Act in this decision, a respondent could give security instead of paying only if it had commenced proceedings in which an independent person or persons, adhering to procedural fairness, would decide the dispute [18], [23]. Referring the dispute to a committee of the parties' own representatives, whose role was to reach agreement, was not enough [26], [27]. Where such a committee is a mandatory first step before any adjudicative tier, a respondent may be unable to commence qualifying proceedings in time and may need to pay rather than give security. The decision is a single first-instance ruling on one contract clause, and readers should check the current text of the Act.

Numbers in square brackets are paragraph numbers of the judgment. This note summarises a decided case for education and is not legal advice. See how the notes are written.